Refer to Construction Management MCQ Questions and Answers in Civil Engineering provided below. Civil Engineering MCQ questions with answers are available for download in Pdf. The MCQ Questions for Civil Engineering with answers are aligned as per the latest syllabus and exam pattern suggested for your exams. Multiple Choice Questions for Construction Management are an important part of exams for Civil Engineering and if practiced properly can help you to improve your understanding of Construction Management and get higher marks. Refer to more Chapter-wise MCQs for Civil Engineering and also download more latest study material for all subjects
MCQ for Civil Engineering Construction Management
Civil Engineering students should refer to the following multiple-choice questions with answers for Construction Management
Construction Management MCQ Questions Civil Engineering with Answers
Question. The pre-tender stage of construction requires ?
a) selection of site
b) acquisition of land
c) finalisation of designs
d) all of these
Answer : D
Question. Float or slack represents the difference between the ?
a) earliest completion time and latest allowable time
b) latest allowable time and earliest completion time
c) earliest completion time and normal expected time
d) latest allowable time and normal allowable time
Answer : A
Question. CPM is ?
a) activity oriented
b) event oriented
c) time oriented
d) resource oriented
Answer : A
Question. PERT analysis is based ?
a) optimistic time
b) pessimistic time
c) most likely time
d) all of these
Answer : D
Question. The early finish time of an activity is the ............ of early start time and duration of activity ?
a) sum
b) difference
c) product
d) ratio
Answer : A
Question. The resources in a construction project are made up of ?
a) plant equipment and machinery required for the project
b) construction materials such as cement, bricks, steel etc
c) skilled and unskilled manpower
d) all of the above
Answer : D
Question. The amount of time by which the activity completion can te start of succeeding activity, is known as ?
a) earliest completion time
b) total float
c) free float
d) none of these
Answer : C
Question. Milestone chart is an improvement over ?
a) bar chart
b) PERT
c) CPM
d) all of these
Answer : A
Question. The jobs going ahead of schedule are conveniently shown in ?
a) Gantt chart
b) milestone chart
c) pie chart
d) none of these
Answer : A
Question. Military type of organisation is known as ?
a) line organisation
b) functional organisation
c) line and staff organisation
d) none of these
Answer : A
Question. The construction of residential building are treated as ?
a) light construction
b) heavy construction
c) industrial construction
d) none of these
Answer : A
Question. In construction work, the controlling function aims at ?
a) keeping a watch over the physical progress of each activity of the work
b) controlling the expenditure on each item of work
c) controlling the use of machines and materials
d) all of the above
Answer : D
Question. The construction works costing below rupees twenty thousand are classified as ?
a) minor works
b) major works
c) projects
d) none of these
Answer : A
Question. The use of bar chart is very popular in construction departments because ?
a) it is very simple to prepare and interpret
b) each item of work or activity is shown separately
c) modification to the chart, if required, can be carried out easily
d) all of the above
Answer : D
Question. A milestone chart ?
a) depicts the delay of job
b) shows the inter dependence of various jobs
c) shows the events in chronological, but not in a logical sequence
d) all of the above
Answer : C
Question. The difference between the total float and free float is called ?
a) duration
b) interfering float
c) critical activity
d) none of these
Answer : B
Question. The estimated time required to complete an activity is known as ?
a) duration
b) float
c) restraint
d) all of these
Answer : A
Question. The start or completion of task is called ?
a) an event
b) an activity
c) a duration
d) any one of these
Answer : B
Question. Probabilistic time for completion of any activity can be found out from ?
a) optimistic time
b) pessimistic time
c) most likely time
d) all of these
Answer : D
Question. The post-tender stage of construction consists of ?
a) assessment of work
b) finalisation of accounts
c) assessment of expenditure during execution
d) all of the above
Answer : D
Question. The contractor is responsible for ?
a) procuring material which is not supplied by the owner
b) organising and planning the work as per drawing
c) executing the work as per specifications laid down in
d) all of the above
Answer : D
Question. The field of activities of an engineer includes ?
a) estimation
b) approval of construction plans by the local authority
c) inspection and payment of work done by contractor
d) all of the above
Answer : D
Question. The process of calculating the resource requirement of a project is known as ?
a) scheduling
b) co-ordinating
c) resource aggregation
d) all of these
Answer : C
Question. F.W. Taylor introduced a system of organisation known as ?
a) line organisation
b) functional organisation
c) line and staff organisation
d) none of these
Answer : B
Question. The conception of idea for any construction work is the responsibility of ?
a) owner
b) engineer
c) contractor
d) all of these
Answer : A
Question. Critical path method ?
a) helps in ascertaining time schedules
b) makes better and detailed planning possible
c) provides a standard method for communicating project plans, schedules time and cost performance
d) all of the above
Answer : D
Question. CPM requires ?
a) single time estimate
b) double time estimate
c) triple time estimate
d) none of these
Answer : D
Question. The construction works costing above rupees one lakh are classified as ?
a) minor works
b) major works
c) projects
d) none of these
Answer : C
Question. In the critical path of construction planning, free float can be ?
a) greater than total float
b) equal to total float
c) greater than independent float
d) less than independent float
Answer : C
Question. Technical planning is carried out for the ?
a) preparation of detailed drawings
b) preparation of detailed estimate
c) planning resources and initiating procurement action
d) all of the above
Answer : D
Question. The construction of ................ belongs to industrial construction ?
a) transit sheds
b) tunnels
c) dams
d) chemical plants
Answer : D
Question. Dummy activities are used to ?
a) determine the critical path
b) determine the project completion time
c) maintain the required net work
d) none of these
Answer : C
Question. PERT requires ?
a) single time estimate
b) double time estimate
c) triple time estimate
d) none of these
Answer : C
Question. In CPM, the cost slope is determined by ?
a) Crash cost / Normal cost
b) Crash cost - Normal cost) / (Normal time - Crash time
c) Normal cost / Crash cost
d) Normal time - Crash time) / (Crash cost - Normal cost
Answer : B
Question. An activity is ?
a) the beginning or end of a specified job
b) an element of work entailed in the project
c) the movement of heavy vehicles from one place to another
d) the progress of work upto a certain limit
Answer : B
Question. A golden rule for the procurement of construction stores is that ?
a) half of the construction stores should be at work site and half under procurement
b) two-third of the construction stores should be at work site and one-third under procurement
c) three-fourth of the construction stores should be at work site and one-fourth under procurement
d) whole of the construction stores should be at work site
Answer : B
Question. Which of the following statement is correct in bar chart planning ?
a) The inter dependence of the operations can be portrayed
b) The progress of work can be measured
c) The spare time of the activities can be determined
d) The schedule can not be updated
Answer : D
Question. The earliest method used for planning of projects was ?
a) CPM
b) PERT
c) bar chart
d) milestone chart
Answer : C
Question. The chart which gives an estimate about the amount of materials handling between various work stations stations is known as ?
a) flow chart
b) time chart
c) travel chart
d) operation chart
Answer : C
Question. An activity requires ?
a) events
b) resources
c) time and resources
d) energy
Answer : C
Question. The total activity slack is equal to ?
a) Late start time - Early start time
b) Late finish time – Early finish time
c) Latest allowable event occurrence time - Early finish time
d) all of the above
Answer : D
Question. The bar chart is also ?
a) flow chart
b) time chart
c) travel chart
d) Gantt chart
Answer : D
Question. Bar chart is suitable for ?
a) large project
b) major work
c) minor work
d) all of these
Answer : C
Question. The construction of airports are treated as ?
a) light construction
b) heavy construction
c) industrial construction
d) none of these
Answer : B
Question. CPM stands for ?
a) Combined Process Method
b) Critical Path Method
c) Common Planning Method
d) Critical Process Method
Answer : B
Question. A construction team includes ?
a) owner
b) engineer
c) architect
d) all of these
Answer : D
Question. The free float is equal to ?
a) Latest allowable event occurrence time + Early finish time
b) Earliest event occurrence time + Early finish time
c) Latest allowable event occurrence time - Early finish time
d) Earliest event occurrence time - Early finish time
Answer : D
Question. The optimistic time represents ?
a) shortest possible time in which an activity can be completed if everything goes exceptionally well
b) time in which the activity is normally expected to complete under normal contingencis
c) time in which an activity will take to complete in case of difficulty
d) none of the above
Answer : A
Question. A critical activity has ?
a) maxitnum float
b) minimum float
c) zero float
d) average float
Answer : C
Question. A bar chart is drawn for ?
a) time versus activity
b) activity versus resources
c) resources versus progress
d) progress versus time
Answer : A
Question. An Assistant Engineer may have powers upto rupees ?
a) twenty five thousand
b) one lakh
c) two lakh
d) two lakh
Answer : A
Question. The occurrence of the starting of an activity, is called its ?
a) head event
b) tail event
c) dual role event
d) none of these
Answer : B
Question. Which of the following statement is correct ?
a) When float of an activity is zero, it falls only on critical path
b) CPM technique is useful to minimise the direct and indirect expenses
c) Critical path of a net work represents the minimum time required for completion of project
d) all of the above
Answer : D
Question. The first stage of a large construction work to ?
a) contract
b) design
c) conception
d) study and evaluation
Answer : A
Question. Which of the following statement is wrong ?
a) An activity consumes time and resources whereas an event do not
b) The performance of a specific task is called an activity
c) An event is an instantaneous point in time at which an activity begins or ends
d) none of the above
Answer : D
Question. The main function of the construction management is ?
a) planning
b) organising
c) directing
d) all of these
Answer : D
Question. The major principle of an organisation is ?
a) span of management
b) unity of command
c) delegation of authority
d) all of these
Answer : D
Question. In a functional organisation ?
a) quality of work is better
b) wastage of material is minimum
c) specialised knowledge and guidance to individual worker is provided
d) all of the above
Answer : D
Question. The final technical authority of a project is ?
a) Assistant Engineer
b) Executive Engineer
c) Superintending Engineer
d) Chief Engineer
Answer : D
Question. A Gantt chart indicates ?
a) balance of work to be done
b) efficiency of project work
c) comparison of actual process with the scheduled progress
d) progress cost of project
Answer : C
Question. A dummy activity in a net work ?
a) is represented by a dotted line
b) is an artificial activity
c) does not consume time or resources
d) all of these
Answer : D
Question. When float or slack of an activity is positive ?
a) it represents a situation where extra resources are available and the completion of project is not delayed
b) it represents that a programme falls behind schedule and additional resources are required to complete the project in time
c) the activity is critical and any delay in its performance will delay the completion of whole project
d) any one of the above
Answer : A
Question. The essential condition for the decompression of an activity is that ?
a) the project time should change due to decompression
b) after decompression, the time of an activity invariably exceeds its normal time
c) an activity could be decompressed to the maximum extent of its normal time
d) none of the above
Answer : C
Question. Time and progress chart are also known as ?
a) bar chart
b) modified milestone chart
c) critical path method chart
d) all of these
Answer : D
Question. Travel charts are used to ?
a) analyse material handling
b) determine inventory control difficulties
c) plan material handling procedure and routes
d) all of the above
Answer : D
Question. The time in which an activity will take to complete in case of difficulty, is called ?
a) optimistic time
b) most likely time
c) pessimistic time
d) none of these
Answer : C
Question. Actual performance of a task is called ?
a) an event
b) an activity
c) a duration
d) any one of these
Answer : B
Question. The salient feature of the organisation evolved by F.W. Taylor is ?
a) strict adherence to specification
b) separation of planning and design part for field work
c) each individual maintains functional efficiency
d) all of the above
Answer : D
Question. The occurrence of the completion of an activity, is called its ?
a) head event
b) tail event
c) dual role event
d) none of these
Answer : A
Question. In a line organisation ?
a) discipline is strong
b) quick decisions are taken
c) responsibility of each individual is fixed
d) all of these
Answer : D
Question. Which of the following are the guidelines for the construction of a network diagram ?
a) Each activity is represented by one and only arrow in the network
b) Dangling must be avoided in a network diagram
c) Dummy activity consumes no time or resource
d) all of the above
Answer : D
Question. PERT ?
a) provides an approach for keeping planning up-to-date
b) provides a way for management to require that planning be done on a uniform and logical basis
c) permits management to foresee quickly the impact of variations from the plan
d) all of the above
Answer : D
Question. Functional organisation system of working was introduced by ?
a) Henry Gantt
b) F.W. Taylor
c) M.R. Walker
d) none of these
Answer : B
Civil Engineering Construction Management MCQs
We hope students liked the above MCQs for Construction Management designed as per the latest syllabus for Civil Engineering. Students should download the Multiple Choice Questions and Answers in Pdf format and practice the questions and solutions given above Civil Engineering MCQs Questions on daily basis. All latest MCQs with answers have been developed for Civil Engineering by referring to the most important and regularly asked topics which the students should learn and practice to get better score in tests and examinations.
MCQs for Civil Engineering Construction Management
Expert teachers of studiestoday have referred to latest book for Civil Engineering to develop the Civil Engineering MCQs. If you download MCQs with answers for the above chapter daily, you will get higher and better marks in test and exams in the current year. Daily Multiple Choice Questions practice of Civil Engineering and its study material will help students to have stronger understanding of all concepts.
Construction Management MCQs Civil Engineering
All MCQs given above for Civil Engineering have been made as per the latest syllabus and books issued for the current academic year. The students can refer to the answers which have been also provided by our teachers for all MCQs of Civil Engineering so that you are able to solve the questions and then compare your answers with the solutions provided by us. We have also provided lot of MCQ questions for Civil Engineering so that you can solve questions relating to all topics given in each chapter. All study material for Civil Engineering students have been given on studiestoday.
Civil Engineering MCQs for Construction Management
Regular MCQs practice helps to gain more practice in solving questions to obtain a more comprehensive understanding of Construction Management concepts. MCQs play an important role in developing understanding of Construction Management. Students can download and save or print all the MCQs, printable assignments, practice sheets of the above chapter in Civil Engineering in Pdf format from studiestoday. After solving these you should also refer to Civil Engineering MCQ Test for the same chapter
MCQs Civil Engineering Construction Management
Civil Engineering best textbooks have been used for writing the problems given in the above MCQs. If you have tests coming up then you should revise all concepts relating to Construction Management and then take out print of the above MCQs and attempt all problems. We have also provided a lot of other MCQs for Civil Engineering which you can use to further make yourself better in Civil Engineering
You can download the MCQs for Civil Engineering Construction Management for latest session from StudiesToday.com
Yes, the MCQs issued for Civil Engineering Construction Management have been made available here for latest academic session
Learning Construction Management based MCQs will help students improve their overall understanding of important concepts and topics and help to score well in Civil Engineering exams.
You can practice Construction Management through worksheets, textbooks and online quizzes provided by studiestoday.com.
You can find Civil Engineering Construction Management MCQs on educational websites like studiestoday.com, online tutoring platforms, and in sample question papers provided on this website.
To prepare for Construction Management MCQs, refer to the concepts links provided by our teachers and download sample papers for free.
Yes, there are many online resources that we have provided on studiestoday.com available such as practice worksheets, question papers, and online tests for learning MCQs for Civil Engineering Construction Management
Yes, you can find printable Construction Management worksheets for Civil Engineering on studiestoday.com.
We have provided full database of free multiple choice questions with answers on studiestoday.com for Civil Engineering Construction Management