Construction Management MCQ Questions and Answers in Civil Engineering

Refer to Construction Management MCQ Questions and Answers in Civil Engineering provided below. Civil Engineering MCQ questions with answers are available for download in Pdf. The MCQ Questions for Civil Engineering with answers are aligned as per the latest syllabus and exam pattern suggested for your exams. Multiple Choice Questions for Construction Management are an important part of exams for Civil Engineering and if practiced properly can help you to improve your understanding of Construction Management and get higher marks. Refer to more Chapter-wise MCQs for Civil Engineering and also download more latest study material for all subjects

MCQ for Civil Engineering Construction Management

Civil Engineering students should refer to the following multiple-choice questions with answers for Construction Management

Construction Management MCQ Questions Civil Engineering with Answers

Question. The pre-tender stage of construction requires ?
a) selection of site
b) acquisition of land
c) finalisation of designs
d) all of these

Answer : D

Question. Float or slack represents the difference between the ?
a) earliest completion time and latest allowable time
b) latest allowable time and earliest completion time
c) earliest completion time and normal expected time
d) latest allowable time and normal allowable time

Answer : A

Question. CPM is ?
a) activity oriented
b) event oriented
c) time oriented
d) resource oriented

Answer : A

Question. PERT analysis is based ?
a) optimistic time
b) pessimistic time
c) most likely time
d) all of these

Answer : D

Question. The early finish time of an activity is the ............ of early start time and duration of activity ?
a) sum
b) difference
c) product
d) ratio

Answer : A

Question. The resources in a construction project are made up of ?
a) plant equipment and machinery required for the project
b) construction materials such as cement, bricks, steel etc
c) skilled and unskilled manpower
d) all of the above

Answer : D

Question. The amount of time by which the activity completion can te start of succeeding activity, is known as ?
a) earliest completion time
b) total float
c) free float
d) none of these

Answer : C

Question. Milestone chart is an improvement over ?
a) bar chart
b) PERT
c) CPM
d) all of these

Answer : A

Question. The jobs going ahead of schedule are conveniently shown in ?
a) Gantt chart
b) milestone chart
c) pie chart
d) none of these

Answer : A

Question. Military type of organisation is known as ?
a) line organisation
b) functional organisation
c) line and staff organisation
d) none of these

Answer : A

Question. The construction of residential building are treated as ?
a) light construction
b) heavy construction
c) industrial construction
d) none of these

Answer : A

Question. In construction work, the controlling function aims at ?
a) keeping a watch over the physical progress of each activity of the work
b) controlling the expenditure on each item of work
c) controlling the use of machines and materials
d) all of the above

Answer : D

Question. The construction works costing below rupees twenty thousand are classified as ?
a) minor works
b) major works
c) projects
d) none of these

Answer : A

Question. The use of bar chart is very popular in construction departments because ?
a) it is very simple to prepare and interpret
b) each item of work or activity is shown separately
c) modification to the chart, if required, can be carried out easily
d) all of the above

Answer : D

Question. A milestone chart ?
a) depicts the delay of job
b) shows the inter dependence of various jobs
c) shows the events in chronological, but not in a logical sequence
d) all of the above

Answer : C

Question. The difference between the total float and free float is called ?
a) duration
b) interfering float
c) critical activity
d) none of these

Answer : B

Question. The estimated time required to complete an activity is known as ?
a) duration
b) float
c) restraint
d) all of these

Answer : A

Question. The start or completion of task is called ?
a) an event
b) an activity
c) a duration
d) any one of these

Answer : B

Question. Probabilistic time for completion of any activity can be found out from ?
a) optimistic time
b) pessimistic time
c) most likely time
d) all of these

Answer : D

Question. The post-tender stage of construction consists of ?
a) assessment of work
b) finalisation of accounts
c) assessment of expenditure during execution
d) all of the above

Answer : D

Question. The contractor is responsible for ?
a) procuring material which is not supplied by the owner
b) organising and planning the work as per drawing
c) executing the work as per specifications laid down in
d) all of the above

Answer : D

Question. The field of activities of an engineer includes ?
a) estimation
b) approval of construction plans by the local authority
c) inspection and payment of work done by contractor
d) all of the above

Answer : D

Question. The process of calculating the resource requirement of a project is known as ?
a) scheduling
b) co-ordinating
c) resource aggregation
d) all of these

Answer : C

Question. F.W. Taylor introduced a system of organisation known as ?
a) line organisation
b) functional organisation
c) line and staff organisation
d) none of these

Answer : B

Question. The conception of idea for any construction work is the responsibility of ?
a) owner
b) engineer
c) contractor
d) all of these

Answer : A

Question. Critical path method ?
a) helps in ascertaining time schedules
b) makes better and detailed planning possible
c) provides a standard method for communicating project plans, schedules time and cost performance
d) all of the above

Answer : D

Question. CPM requires ?
a) single time estimate
b) double time estimate
c) triple time estimate
d) none of these

Answer : D

Question. The construction works costing above rupees one lakh are classified as ?
a) minor works
b) major works
c) projects
d) none of these

Answer : C

Question. In the critical path of construction planning, free float can be ?
a) greater than total float
b) equal to total float
c) greater than independent float
d) less than independent float

Answer : C

Question. Technical planning is carried out for the ?
a) preparation of detailed drawings
b) preparation of detailed estimate
c) planning resources and initiating procurement action
d) all of the above

Answer : D

Question. The construction of ................ belongs to industrial construction ?
a) transit sheds
b) tunnels
c) dams
d) chemical plants

Answer : D

Question. Dummy activities are used to ?
a) determine the critical path
b) determine the project completion time
c) maintain the required net work
d) none of these

Answer : C

Question. PERT requires ?
a) single time estimate
b) double time estimate
c) triple time estimate
d) none of these

Answer : C

Question. In CPM, the cost slope is determined by ?
a) Crash cost / Normal cost
b) Crash cost - Normal cost) / (Normal time - Crash time
c) Normal cost / Crash cost
d) Normal time - Crash time) / (Crash cost - Normal cost

Answer : B

Question. An activity is ?
a) the beginning or end of a specified job
b) an element of work entailed in the project
c) the movement of heavy vehicles from one place to another
d) the progress of work upto a certain limit

Answer : B

Question. A golden rule for the procurement of construction stores is that ?
a) half of the construction stores should be at work site and half under procurement
b) two-third of the construction stores should be at work site and one-third under procurement
c) three-fourth of the construction stores should be at work site and one-fourth under procurement
d) whole of the construction stores should be at work site

Answer : B

Question. Which of the following statement is correct in bar chart planning ?
a) The inter dependence of the operations can be portrayed
b) The progress of work can be measured
c) The spare time of the activities can be determined
d) The schedule can not be updated

Answer : D

Question. The earliest method used for planning of projects was ?
a) CPM
b) PERT
c) bar chart
d) milestone chart

Answer : C

Question. The chart which gives an estimate about the amount of materials handling between various work stations stations is known as ?
a) flow chart
b) time chart
c) travel chart
d) operation chart

Answer : C

Question. An activity requires ?
a) events
b) resources
c) time and resources
d) energy

Answer : C

Question. The total activity slack is equal to ?
a) Late start time - Early start time
b) Late finish time – Early finish time
c) Latest allowable event occurrence time - Early finish time
d) all of the above

Answer : D

Question. The bar chart is also ?
a) flow chart
b) time chart
c) travel chart
d) Gantt chart

Answer : D

Question. Bar chart is suitable for ?
a) large project
b) major work
c) minor work
d) all of these

Answer : C

Question. The construction of airports are treated as ?
a) light construction
b) heavy construction
c) industrial construction
d) none of these

Answer : B

Question. CPM stands for ?
a) Combined Process Method
b) Critical Path Method
c) Common Planning Method
d) Critical Process Method

Answer : B

Question. A construction team includes ?
a) owner
b) engineer
c) architect
d) all of these

Answer : D

Question. The free float is equal to ?
a) Latest allowable event occurrence time + Early finish time
b) Earliest event occurrence time + Early finish time
c) Latest allowable event occurrence time - Early finish time
d) Earliest event occurrence time - Early finish time

Answer : D

Question. The optimistic time represents ?
a) shortest possible time in which an activity can be completed if everything goes exceptionally well
b) time in which the activity is normally expected to complete under normal contingencis
c) time in which an activity will take to complete in case of difficulty
d) none of the above

Answer : A

Question. A critical activity has ?
a) maxitnum float
b) minimum float
c) zero float
d) average float

Answer : C

Question. A bar chart is drawn for ?
a) time versus activity
b) activity versus resources
c) resources versus progress
d) progress versus time

Answer : A

Question. An Assistant Engineer may have powers upto rupees ?
a) twenty five thousand
b) one lakh
c) two lakh
d) two lakh

Answer : A

Question. The occurrence of the starting of an activity, is called its ?
a) head event
b) tail event
c) dual role event
d) none of these

Answer : B

Question. Which of the following statement is correct ?
a) When float of an activity is zero, it falls only on critical path
b) CPM technique is useful to minimise the direct and indirect expenses
c) Critical path of a net work represents the minimum time required for completion of project
d) all of the above

Answer : D

Question. The first stage of a large construction work to ?
a) contract
b) design
c) conception
d) study and evaluation

Answer : A

Question. Which of the following statement is wrong ?
a) An activity consumes time and resources whereas an event do not
b) The performance of a specific task is called an activity
c) An event is an instantaneous point in time at which an activity begins or ends
d) none of the above

Answer : D

Question. The main function of the construction management is ?
a) planning
b) organising
c) directing
d) all of these

Answer : D

Question. The major principle of an organisation is ?
a) span of management
b) unity of command
c) delegation of authority
d) all of these

Answer : D

Question. In a functional organisation ?
a) quality of work is better
b) wastage of material is minimum
c) specialised knowledge and guidance to individual worker is provided
d) all of the above

Answer : D

Question. The final technical authority of a project is ?
a) Assistant Engineer
b) Executive Engineer
c) Superintending Engineer
d) Chief Engineer

Answer : D

Question. A Gantt chart indicates ?
a) balance of work to be done
b) efficiency of project work
c) comparison of actual process with the scheduled progress
d) progress cost of project

Answer : C

Question. A dummy activity in a net work ?
a) is represented by a dotted line
b) is an artificial activity
c) does not consume time or resources
d) all of these

Answer : D

Question. When float or slack of an activity is positive ?
a) it represents a situation where extra resources are available and the completion of project is not delayed
b) it represents that a programme falls behind schedule and additional resources are required to complete the project in time
c) the activity is critical and any delay in its performance will delay the completion of whole project
d) any one of the above

Answer : A

Question. The essential condition for the decompression of an activity is that ?
a) the project time should change due to decompression
b) after decompression, the time of an activity invariably exceeds its normal time
c) an activity could be decompressed to the maximum extent of its normal time
d) none of the above

Answer : C

Question. Time and progress chart are also known as ?
a) bar chart
b) modified milestone chart
c) critical path method chart
d) all of these

Answer : D

Question. Travel charts are used to ?
a) analyse material handling
b) determine inventory control difficulties
c) plan material handling procedure and routes
d) all of the above

Answer : D

Question. The time in which an activity will take to complete in case of difficulty, is called ?
a) optimistic time
b) most likely time
c) pessimistic time
d) none of these

Answer : C

Question. Actual performance of a task is called ?
a) an event
b) an activity
c) a duration
d) any one of these

Answer : B

Question. The salient feature of the organisation evolved by F.W. Taylor is ?
a) strict adherence to specification
b) separation of planning and design part for field work
c) each individual maintains functional efficiency
d) all of the above

Answer : D

Question. The occurrence of the completion of an activity, is called its ?
a) head event
b) tail event
c) dual role event
d) none of these

Answer : A

Question. In a line organisation ?
a) discipline is strong
b) quick decisions are taken
c) responsibility of each individual is fixed
d) all of these

Answer : D

Question. Which of the following are the guidelines for the construction of a network diagram ?
a) Each activity is represented by one and only arrow in the network
b) Dangling must be avoided in a network diagram
c) Dummy activity consumes no time or resource
d) all of the above

Answer : D

Question. PERT ?
a) provides an approach for keeping planning up-to-date
b) provides a way for management to require that planning be done on a uniform and logical basis
c) permits management to foresee quickly the impact of variations from the plan
d) all of the above

Answer : D

Question. Functional organisation system of working was introduced by ?
a) Henry Gantt
b) F.W. Taylor
c) M.R. Walker
d) none of these

Answer : B

Civil Engineering MCQ Questions and Answers
Advanced Construction and Equipments MCQ Questions and Answers in Civil Engineering
Airport Engineering MCQ Questions and Answers in Civil Engineering
Applied Mechanics and Graphic Statics MCQ Questions and Answers in Civil Engineering
Basics of Civil Engineering MCQ Questions and Answers in Civil Engineering
Building Construction MCQ Questions and Answers in Civil Engineering
Building Maintenance MCQ Questions and Answers in Civil Engineering
Building Materials MCQ Questions and Answers in Civil Engineering
Building Services MCQ Questions and Answers in Civil Engineering
Building Technology and Architectural Planning MCQ Questions and Answers in Civil Engineering
Concrete Technology and Design of Concrete Structures MCQ Questions and Answers in Civil Engineering
Concrete Technology MCQ Questions and Answers in Civil Engineering
Construction Management MCQ Questions and Answers in Civil Engineering
Construction Technology MCQ Questions and Answers in Civil Engineering
Design of Masonry Structures MCQ Questions and Answers in Civil Engineering
Docks and Harbor Engineering MCQ Questions and Answers in Civil Engineering
Elements of Remote Sensing MCQ Questions and Answers in Civil Engineering
Engineering Economics MCQ Questions and Answers in Civil Engineering
Engineering Geology MCQ Questions and Answers in Civil Engineering
Engineering Graphics MCQ Questions and Answers in Civil Engineering
Engineering Mechanics MCQ Questions and Answers in Civil Engineering
Environmental Engineering MCQ Questions and Answers in Civil Engineering
Estimating and Costing MCQ Questions and Answers in Civil Engineering
Estimation Costing and Valuation Engineering MCQ Questions and Answers in Civil Engineering
Geotechnical Engineering MCQ Questions and Answers in Civil Engineering
Highway Engineering MCQ Questions and Answers in Civil Engineering
Hydraulic Machines MCQ Questions and Answers in Civil Engineering
Hydraulics and Fluid Mechanics MCQ Questions and Answers in Civil Engineering
Irrigation Engineering MCQ Questions and Answers in Civil Engineering
Maintenance and Rehabilitation of Structures MCQ Questions and Answers in Civil Engineering
Prefabricated Structures MCQ Questions and Answers in Civil Engineering
Professional Ethics in Engineering MCQ Questions and Answers in Civil Engineering
Public Health Engineering MCQ Questions and Answers in Civil Engineering
Railway Bridge and Tunnel Engineering MCQ Questions and Answers in Civil Engineering
Railway Engineering MCQ Questions and Answers in Civil Engineering
RCC Structures Design MCQ Questions and Answers in Civil Engineering
Reinforced Cement Concrete Structures MCQ Questions and Answers in Civil Engineering
Societal and Global Impact MCQ Questions and Answers in Civil Engineering
Soil Mechanics and Foundations MCQ Questions and Answers in Civil Engineering
Steel Structures Design MCQ Questions and Answers in Civil Engineering
Strength of Materials MCQ Questions and Answers in Civil Engineering
Structural Analysis MCQ Questions and Answers in Civil Engineering
Structural Design and Drawing MCQ Questions and Answers in Civil Engineering
Structural Mechanics MCQ Questions and Answers in Civil Engineering
Surveying MCQ Questions and Answers in Civil Engineering
Theory of Structures MCQ Questions and Answers in Civil Engineering
Tunnel Engineering MCQ Questions and Answers in Civil Engineering
Waste Water Engineering MCQ Questions and Answers in Civil Engineering
Waste Water Treatment MCQ Questions and Answers in Civil Engineering
Water Supply Engineering MCQ Questions and Answers in Civil Engineering

Civil Engineering Construction Management MCQs

We hope students liked the above MCQs for Construction Management designed as per the latest syllabus for Civil Engineering. Students should download the Multiple Choice Questions and Answers in Pdf format and practice the questions and solutions given above Civil Engineering MCQs Questions on daily basis. All latest MCQs with answers have been developed for Civil Engineering by referring to the most important and regularly asked topics which the students should learn and practice to get better score in tests and examinations.

MCQs for Civil Engineering Construction Management

Expert teachers of studiestoday have referred to latest book for Civil Engineering to develop the Civil Engineering MCQs. If you download MCQs with answers for the above chapter daily, you will get higher and better marks in test and exams in the current year. Daily Multiple Choice Questions practice of Civil Engineering and its study material will help students to have stronger understanding of all concepts.

Construction Management MCQs Civil Engineering

All MCQs given above for Civil Engineering have been made as per the latest syllabus and books issued for the current academic year. The students can refer to the answers which have been also provided by our teachers for all MCQs of Civil Engineering so that you are able to solve the questions and then compare your answers with the solutions provided by us. We have also provided lot of MCQ questions for Civil Engineering so that you can solve questions relating to all topics given in each chapter. All study material for Civil Engineering students have been given on studiestoday.

Civil Engineering MCQs for Construction Management

Regular MCQs practice helps to gain more practice in solving questions to obtain a more comprehensive understanding of Construction Management concepts. MCQs play an important role in developing understanding of Construction Management. Students can download and save or print all the MCQs, printable assignments, practice sheets of the above chapter in Civil Engineering in Pdf format from studiestoday. After solving these you should also refer to Civil Engineering MCQ Test for the same chapter

MCQs Civil Engineering Construction Management

Civil Engineering best textbooks have been used for writing the problems given in the above MCQs. If you have tests coming up then you should revise all concepts relating to Construction Management and then take out print of the above MCQs and attempt all problems. We have also provided a lot of other MCQs for Civil Engineering which you can use to further make yourself better in Civil Engineering

Where can I download latest MCQs for Civil Engineering Construction Management

You can download the MCQs for Civil Engineering Construction Management for latest session from StudiesToday.com

Are the Civil Engineering Construction Management MCQs available for the latest session

Yes, the MCQs issued for Civil Engineering Construction Management have been made available here for latest academic session

Why are Construction Management important for students?

Learning Construction Management based MCQs will help students improve their overall understanding of important concepts and topics and help to score well in Civil Engineering exams.

How can I practice Construction Management Questions?

You can practice Construction Management through worksheets, textbooks and online quizzes provided by studiestoday.com.

Where can I find Civil Engineering Construction Management MCQs online?

You can find Civil Engineering Construction Management MCQs on educational websites like studiestoday.com, online tutoring platforms, and in sample question papers provided on this website.

How can I prepare for Construction Management MCQs?

To prepare for Construction Management MCQs, refer to the concepts links provided by our teachers and download sample papers for free.

Are there any online resources for Civil Engineering Construction Management?

Yes, there are many online resources that we have provided on studiestoday.com available such as practice worksheets, question papers, and online tests for learning MCQs for Civil Engineering Construction Management

Can I find Civil Engineering Construction Management practice worksheets online?

Yes, you can find printable Construction Management worksheets for Civil Engineering on studiestoday.com.

How can I get more free MCQs with answers for Civil Engineering Construction Management MCQs?

We have provided full database of free multiple choice questions with answers on studiestoday.com for Civil Engineering Construction Management