Refer to Time and Work CUET General Test MCQs provided below available for download in Pdf. The MCQ Questions for CUET General Test with answers are aligned as per the latest syllabus and exam pattern suggested by CUET, NCERT and KVS. Time and Work CUET MCQ are an important part of exams for CUET General Test and if practiced properly can help you to improve your understanding and get higher marks. Refer to more Chapter-wise MCQs for CUET CUET General Test and also download more latest study material for all subjects
MCQ for CUET General Test Time and Work
CUET General Test students should refer to the following multiple-choice questions with answers for Time and Work in CUET.
Time and Work MCQ Questions CUET General Test with Answers
Question: 30 men can produce 1500 units in 24 days working 6 h a day. In how many days, can 18 men produce 1800 units working 8 h a day?
a) 18
b) 32
c) 36
d) 45
Answer: c
Question: 15 trackmen complete rail renewal job in 12 days. How many days would 18 trackmen take to complete the same job?
a) 10
b) 18
c) 15
d) 17
Answer: a
Question: A can do 3/4 of a work in 12 days. In how many days can he finish 1/8 of the work?
a) 1
b) 2
c) 3
d) 4
Answer: b
Question: A can do a piece of work in 10 days and B can do the same piece of work in 20 days. They start the work together, but after 5 days A leaves. B will do the remaining piece of work in
a) 5 days
b) 10 days
c) 6 days
d) 8 days
Answer: a
Question: Three pipes A, B and C can fill a tank in 30 min, 20 min and 10 min, respectively. When the tank is empty, all the three pipes are opened. If A, B and C discharge chemical solutions P, Q and R respectively, then the part of solution R in the liquid in the tank after 3 min is
a) 8/11
b) 5/11
c) 6/11
d) 7/11
Answer: c
Question: 8 horses’ food is equal to 6 cows’ food. How many cows can eat the food meant for 20 horses?
a) 15
b) 16
c) 17
d) 18
Answer: a
Question: A, B and C can do a piece of work in 20, 24 and 30 days, respectively. They undertook to do the piece of work for Rs 5400. They begin the work together but B left 2 days before the completion of work and C left 5 days before the completion of work. The share of A from the assured money is
a) Rs 2700
b) Rs 540
c) Rs 1800
d) Rs 600
Answer: a
Question: 4 men and 6 childern can complete a work in 8 days while 3 men and 7 childern can complete the same work in 10 days. If 20 childern only work, the work will be completed in
a) 20 days
b) 22 days
c) 15 days
d) 18 days
Answer: a
Question: A and B can do a piece of work in 72 days, B and C can do it in 120 days, and A and C can do it in 90 days. When A, B and C work together, how much work is finished by them in 3 days?
a) 1/40
b) 1/30
c) 1/20
d) 1/10
Answer: b
Question: A and B can do a piece of work in 8 days, B and C can do it in 24 days, while C and A can do it in 8 4/7 days. In how many days can C do it alone?
a) 60
b) 40
c) 30
d) 10
Answer: a
Question: A and B undertake to do a piece of work for Rs 720. A alone can do it in 8 days and B alone can do it in 12 days. With the help of C they finish it in 4 days. Then, the share of C (in Rs) is
a) 120
b) 300
c) 360
d) 240
Answer: a
Question: A man can do a work in 15 days. His father do this work in 20 days and man’s son do this work in 25 days. If all do the work together, how many days will they take?
a) Less than 6 days
b) 6 days
c) Approximately 6.4 days
d) More than 10 days
Answer: a
Question: A is thrice as good a workman as B and therefore is able to finish a job in 40 days less than B. Working together, they can do it in
a) 14 days
b) 13 days
c) 20 days
d) 15 days
Answer: d
Question: If 6 men and 8 boys can do a piece of work in 10 days, while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be
a) 4 days
b) 5 days
c) 6 days
d) 7 days
Answer: a
Question: A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is
a) 1/4
b) 1/10
c) 7/15
d) 8/15
Answer: d
Question: A coach helper repairs a coach in 12 days. His technician completes the same job in 18 days. If both of them work together, in how many days would the job be completed?
a) 5/36
b) 7.3
c) 7.2
d) 7
Answer: c
Question: X can complete a piece of work in 30 h and Y can do it in 24 h. In how many hours will it be completed if they work together?
a) 13.33
b) 14.33
c) 15.33
d) 16.33
Answer: a
Question: If 18 men and 10 boys can do in one day as much work as 10 men and 22 boys, the amount that a men should be paid per day, if a boy gets Rs 10 per day
a) Rs 7.5
b) Rs 12.5
c) Rs 20
d) Rs 15
Answer: d
Question: A is twice as good a workman as B and together they finish a piece of work in 14 days. The number of days taken by A alone to finish the work is
a) 11 days
b) 21 days
c) 28 days
d) 42 days
Answer: b
Question: After working for 8 days, Anil finds that only 1/3 of the work has been done. He employs Rakesh who is 60% efficient as Anil. How many more days will Anil take to complete the job
a) 5
b) 8
c) 10
d) 12
Answer: c
Question: A is thrice as efficient as B and B is twice as efficient as C, if A, B and C work together how long would they take to complete a job that B takes 10 days to complete?
a) 20/9 days
b) 11/9 days
c) 3 days
d) None of these
Answer: a
Question: A, B and C can do a job alone in 6, 12 and 24 days respectively. In what time will they do it together?
a) 2 3/7 days
b) 3 3/7 days
c) 3 2/7 days
d) 3 4/7 days
Answer: b
Question: Rani and Sneha working separately can finish a job in 8 h and 12 h respectively. If they work for an hour alternately, Rani beginning at 9 : 00 am when will the job be finished?
a) 7 : 30 pm
b) 7 : 00 pm
c) 6 : 30 pm
d) 6 : 00 pm
Answer: c
Question: 12 men can complete a work in 18 days. 6 days after they started working, 4 men joined them. How many days will all of them take to finish the remaining work?
a) 9
b) 10
c) 12
d) 15
Answer: a
Question: 12 boys can do a piece of work in 16 days. In how many days can 6 boys do the same work?
a) 16 days
b) 32 days
c) 23 days
d) 24 days
Answer: b
Question: Working 7 hours daily 24 men can complete a piece of work in 27 days. In how many days would 14 men complete the same piece of work working 9 hours daily?
a) 32 days
b) 31 days
c) 36 days
d) 39 days
Answer: c
Question: A and B working together complete a work in 35 days. If A takes 60 days to complete it, how long would B alone take to complete it?
a) 64 days
b) 72 days
c) 81 days
d) 84 days
Answer: d
Question: A can do a piece of work in 40 days. He starts working, but having some other engagements he drops out after 5 days. Thereafter B completes this work in 21 days. How many days would A and B take to complete this work working together?
a) 15 days
b) 16 days
c) 17 days
d) 11 days
Answer: a
Question: A can do a piece of work in 4 days. B is 50% more efficient than A. How long would B alone take to finish this work?
a) 3 1/3 days
b) 5 1/4 days
c) 2 2/3 days
d) 1 2/3 days
Answer: c
Question: Two persons A and B can complete a piece of work in 8 hours and 16 hours respectively. If they work at it alternately for an hour, A starting first, in how many hours will the work be finished?
a) 9 1/3 hours
b) 10 1/2 hours
c) 11 1/2 hours
d) 8 1/2 hours
Answer: b
Question: Two pipes can fill a tank in 8 hours and 12 hours respectively whereas an escape pipe can empty it in 6 hours. If the three pipes are opened at 1 p.m., 2 p.m. and 3 p.m. respectively, at what time will the tank be filled?
a) 7.00 a.m.
b) 8.00 a.m.
c) 5.00 a.m.
d) 7.30 a.m.
Answer: a
Question: A few children working together can do a piece of work in 18 days. If the number of children employed on the work is made double, how long would they take to complete half of the work?
a) 4 1/2 days
b) 2 1/3 days
c) 8 3/4 days
d) 6 1/2 days
Answer: a
Question: A can do a piece of work in 8 days while B can do the same work in 16 days. If they start working together, how long would they take to complete half portion of this work?
a) 2 2/3 days
b) 3 5/7 days
c) 4 1/2 days
d) 3 1/2 days
Answer: a
Question: A and B working together can complete a piece of work in 12 days and B and C working together can complete the same work in 16 days. A worked at it for 5 days and B worked at it for 7 days. C finished the remaining work in 13 days. How many days would C alone take to complete it?
a) 10 days
b) 24 days
c) 32 days
d) 40 days
Answer: b
Question: 10 men or 18 boys can do a piece of work in 15 days. In how many days would 25 men and 15 boys complete the same work working together?
a) 5 1/2 days
b) 4 1/2 days
c) 6 2/3 days
d) 2 1/3 days
Answer: b
Question: 15 men can complete a work in 210 days. They started the work but at the end of 10 days 15 additional men, with double efficiency, were inducted) How many days, in whole, did they take to finish the work?
a) 76 2/3 days
b) 84 3/4 days
c) 72 1/2 days
d) 70 days
Answer: a
Question: A is twice as good a workman as B and thrice as good a workman as c) If C alone can do a piece of work in 24 days, how long would the three persons take to finish the work working together?
a) 3 3/11 days
b) 4 4/7 days
c) 4 4/11 days
d) 3 4/11 days
Answer: c
Question: A cistern is filled by a tap in 3 1/2 hours. Due to a leak in the bottom of the cistern, it takes half an hour longer to fill the cistern. If the cistern is full, how long will it take the leak to empty it?
a) 28 hours
b) 29 hours
c) 31 1/3 hours
d) 38 hours
Answer: a
Question: A, B and C undertake to do a piece of work for Rs 529. If A and B working together do 19/23 work and B and C working together do 8/23 work, how should the money be divided among them?
a) Rs 345, Rs 102, Rs 82
b) Rs 345, Rs 92, Rs 92
c) Rs 330, Rs 107, Rs 92
d) Rs 330, Rs 92, Rs 107
Answer: b
Attempt Mock Tests on this topic
MCQs for Time and Work General Test CUET
Expert teachers of studiestoday have referred to NCERT book for CUET General Test to develop the General Test CUET MCQs. If you download MCQs with answers for the above chapter you will get higher and better marks in CUET test and exams in the current year as you will be able to have stronger understanding of all concepts. Daily Multiple Choice Questions practice of General Test will help students to have stronger understanding of all concepts and also make them expert on all critical topics. After solving the questions given in the MCQs which have been developed as per latest books also refer to the NCERT solutions for CUET General Test. We have also provided lot of MCQ questions for CUET General Test so that you can solve questions relating to all topics given in each chapter. After solving these you should also refer to CUET General Test MCQ Test for the same chapter.
You can download the CUET MCQs for CUET General Test Time and Work for latest session from StudiesToday.com
Yes, the MCQs issued by CUET for CUET General Test Time and Work have been made available here for latest academic session
You can find CUET CUET General Test Time and Work MCQs on educational websites like studiestoday.com, online tutoring platforms, and in sample question papers provided on this website.
To prepare for Time and Work MCQs, refer to the concepts links provided by our teachers and download sample papers for free.
Yes, there are many online resources that we have provided on studiestoday.com available such as practice worksheets, question papers, and online tests for learning MCQs for CUET General Test Time and Work