Refer to CBSE Class 4 Mathematics Time and Work MCQs provided below available for download in Pdf. The MCQ Questions for Class 4 Mathematics with answers are aligned as per the latest syllabus and exam pattern suggested by CBSE, NCERT and KVS. Multiple Choice Questions for Time and Work are an important part of exams for Class 4 Mathematics and if practiced properly can help you to improve your understanding and get higher marks. Refer to more Chapter-wise MCQs for CBSE Class 4 Mathematics and also download more latest study material for all subjects
MCQ for Class 4 Mathematics Time and Work
Class 4 Mathematics students should refer to the following multiple-choice questions with answers for Time and Work in Class 4.
Time and Work MCQ Questions Class 4 Mathematics with Answers
Question. A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in ?
a) 60 days
b) 120 days
c) 80 days
d) 30 days
Answer : B
Question. 7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
a) 28
b) 21
c) 14
d) 7
Answer : C
Question. A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in ?
a) 5 days
b) 7 days
c) 11 days
d) 3 days
Answer : A
Question. A can do as much work as B and C together can do. A and B can together do a piece of work in 9 hours 36 minutes and C can do it in 48 hours. The time (in hours) that B needs to do the work alone, is ?
a) 18 hrs
b) 24 hrs
c) 30 hrs
d) 12 hrs
Answer : B
Question. A and B together can complete a work in 8 days. B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone take to complete the work ?
a) 15 days
b) 18 days
c) 16 days
d) 20 days
Answer : C
Question. 6 men and 8 women can do a work in 10 days, Then 3 men and 4 women can do the same work in ?
a) 24 days
b) 20 days
c)12 days
d) 18 days
Answer : B
Question. A is thrice as good a workman as B and therefore is able to finish a job in 40 days less than B. Working together, they can do it in ?
a) 14 days
b) 13 days
c) 20 days
d) 15 days
Answer : D
Question. A and B were assigned to do a job for an amount of 1,200. A alone can do it in 15 days, while B can do it in 12 days. With the help of C, they can finish in 5 days. The share of amount that C earns is ?
a) 300
b) 400
c) 500
d) 600
Answer : A
Question.A father can do a job as fast as his two sons working together. If one son does the job in 3 hours and the other in 6 hours, the number of hours taken by the father, to do the job alone is ?
a) 1
b) 2
c) 3
d) 4
Answer : B
Question. If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work ?
a) 60 days
b) 45 days
c) 40 days
d) 30 days
Answer : A
Question. If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is ?
a) 38
b) 28
c) 19
d) 17
Answer : B
Question. A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day ?
a) 10 days
b) 12 days
c) 15 days
d) 20 days
Answer : C
Question. A can do 1/6 of a work in 5 days and B can do 2/5 of the work in 8 days. In how many days, can both A and B together do the work ?
a) 12 days
b) 13 days
c) 15 days
d) 20 days
Answer : A
Question. If there is a reduction in the number of workers in a factory in the ratio 15 : 11 and an increment in their wages in the ratio 22 : 25, then the ratio by which the total wages of the workers should be decreased is ?
a) 6 : 5
b) 5 : 6
c) 3 : 7
d) 3 :5
Answer : A
Question.20 men working 8 hours per day can complete a piece of work in 21 days. How many hours per day must 48 men work to complete the same job in 7 days ?
a) 12
b) 20
c) 10
d) 15
Answer : C
Question. 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it ?
a) 50 days
b) 45 days
c) 40 days
d) 35 days
Answer : C
Question. x does 1/4 of a job in 6 days. y completes rest of the job in 12 days. Then x and y could complete the job together in ?
a) 9 days
b) 9 and 3/5 days
c) 8 and 1/8 days
d) 7 and 1/3 days
Answer : B
Question. A and B together can do a piece of work in 9 days. If A does thrice the work of B in a given time, the time A alone will take to finish the work is ?
a) 4 days
b) 6 days
c) 8 days
d) 12 days
Answer : D
Question. 12 men and 16 boys can do a piece of work in 5 days; 13 men and 24 boys can do it in 4 days, then the ratio of the daily work done by a man to that of a boy is ?
a)2 : 1
b) 3 : 1
c) 1 : 3
d) 5 : 4
Answer : A
Question. If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be ?
a) 12 days
b) 10 days
c) 9 days
d) 8 days
Answer : B
Question.If 20 women can lay a road of length 100m in 10 days. Then 10 women can lay the same road of length 50 m in ?
a) 20 days
b) 15 days
c) 5 days
d) 10 days
Answer : D
Question. If A and B together can complete a work in 18 days, A and C together in 12 days and B and C together in 9 days, then B alone can do the work in ?
a)18 days
b) 24 days
c) 30 days
d) 40 days
Answer : B
Question. A can do a piece of work in 12 days and B in 24 days. If they work together, in how many days will they finish the work ?
a) 12 days
b) 20 days
c) 15 days
d) 8 days
Answer : D
Question. A and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. C alone will finish the job in ?
a) 12 days
b) 14 days
c) 16 days
d) 24 days
Answer : A
Question. A man is twice as fast as a woman and a woman is twice as fast as a boy in doing a work. If all of them, a man, a woman and a boy can finish the work in 7 days, in how many days a boy will do it alone ?
a) 49
b) 7
c) 6
d) 42
Answer : A
Question. A is 30% more efficient than B, and can alone do a work in 23 days. The number of days, in which A and B, working together can finish the job is ?
a) 11 days
b) 13 days
c) 20 days
d) 21 days
Answer : B
Question.8 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 days, working 9 hours a day. Find how many workers will be able to build a wall 32 m long, 3 m broad and 9 m high in 8 days working 6 hours a day ?
a) 16
b) 20
c) 30
d) 10
Answer : C
Question. 4 mat-weavers can weave 4 mats in 4 days. At the same rate how many mats would be woven by 8 mat-weavers in 8 days ?
a) 4
b) 8
c) 12
d) 16
Answer : D
Question. A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together ?
a) 4 days
b) 6 days
c) 2 days
d) 3 days
Answer : D
Question. Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work than when work together. If B worked alone, would take 4 and 1/2 hours more than when work together. The time required to finish the work together is ?
a) 5 hours
b) 4 hours
c) 8 hours
d) 6 hours
Answer : D
Question. A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last ?
a) 10 days
b) 20 days
c) 15 days
d) 6 days
Answer : A
Question. 20 men can do a piece of work in 18 days, They worked together for 3 days, then 5 men joined them. In how many more days is the work completed ?
a) 15
b) 12
c) 14
d) 13
Answer : B
Question.If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then the number of chairs made by 18 carpenters in 36 days each working 8 hours a day is ?
a) 92
b) 132
c) 138
d) 126
Answer : C
Question. If 5 men or 7 women can earn 5,250 per day, how much would 7 men and 13 women earn per day ?
a) 11,600
b) 11,700
c) 16,100
d) 17,100
Answer : D
Question. A canal of a village can be cleaned by 24 villagers in 12 days. The number of days in which 36 villagers can clean the canal is ?
a) 18
b) 8
c) 72
d) 16
Answer : B
Question. Sunil completes a work in 4 days, whereas Dinesh completes the work in 6 days. Ramesh works 1 and 1/2 times as fast as Sunil. The three together can complete the work in ?
a) 1 and 5/12 days
b) 1 and 5/7 days
c) 1 and 3/8 days
d) 1 and 5/19 days
Answer : D
Question. A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in ?
a) 16 days
b) 24 days
c) 28 days
d) 29 days
Answer : B
Question. If 1 man or 2 women or 3 boys can complete a piece of work in 88 days, then 1 man, 1 woman and 1 boy together will complete it in ?
a) 36 days
b) 42 days
c) 48 days
d) 54 days
Answer : C
Question. A can do a work in 10 days and B in 20 days. If they together work on it for 5 days, then the fraction of the work that is left is ?
a) 3/4
b) 4/3
c) 3/20
d) 1/4
Answer : D
MCQs for Mathematics CBSE Class 4 Time and Work
Expert teachers of studiestoday have referred to NCERT book for Class 4 Mathematics to develop the Mathematics Class 4 MCQs. If you download MCQs with answers for the above chapter daily, you will get higher and better marks in Class 4 test and exams in the current year as you will be able to have stronger understanding of all concepts. Daily Multiple Choice Questions practice of Mathematics and its study material will help students to have stronger understanding of all concepts and also make them expert on all critical topics. After solving the questions given in the MCQs which have been developed as per latest course books also refer to the NCERT solutions for Class 4 Mathematics designed by our teachers
Time and Work MCQs Mathematics CBSE Class 4
All MCQs given above for Class 4 Mathematics have been made as per the latest syllabus and books issued for the current academic year. The students of Class 4 can refer to the answers which have been also provided by our teachers for all MCQs of Mathematics so that you are able to solve the questions and then compare your answers with the solutions provided by us. We have also provided lot of MCQ questions for Class 4 Mathematics so that you can solve questions relating to all topics given in each chapter. All study material for Class 4 Mathematics students have been given on studiestoday.
Time and Work CBSE Class 4 MCQs Mathematics
Regular MCQs practice helps to gain more practice in solving questions to obtain a more comprehensive understanding of Time and Work concepts. MCQs play an important role in developing understanding of Time and Work in CBSE Class 4. Students can download and save or print all the MCQs, printable assignments, practice sheets of the above chapter in Class 4 Mathematics in Pdf format from studiestoday. You can print or read them online on your computer or mobile or any other device. After solving these you should also refer to Class 4 Mathematics MCQ Test for the same chapter
CBSE MCQs Mathematics Class 4 Time and Work
CBSE Class 4 Mathematics best textbooks have been used for writing the problems given in the above MCQs. If you have tests coming up then you should revise all concepts relating to Time and Work and then take out print of the above MCQs and attempt all problems. We have also provided a lot of other MCQs for Class 4 Mathematics which you can use to further make yourself better in Mathematics
You can download the CBSE MCQs for Class 4 Mathematics Time and Work for latest session from StudiesToday.com
Yes, you can click on the links above and download topic wise MCQs Questions PDFs for Time and Work Class 4 for Mathematics
Yes, the MCQs issued by CBSE for Class 4 Mathematics Time and Work have been made available here for latest academic session
You can easily access the links above and download the Time and Work Class 4 MCQs Mathematics for each topic
There is no charge for the MCQs and their answers for Class 4 CBSE Mathematics Time and Work you can download everything free
Regular revision of MCQs given on studiestoday for Class 4 subject Mathematics Time and Work can help you to score better marks in exams
Multiple Choice Questions (MCQs) for Time and Work Class 4 Mathematics are objective-based questions which provide multiple answer options, and students are required to choose the correct answer from the given choices.
Learning Time and Work based MCQs will help students improve their overall understanding of important concepts and topics and help to score well in Class 4 Mathematics exams.
You can practice Time and Work for CBSE Class 4 through worksheets, textbooks and online quizzes provided by studiestoday.com.
You can find CBSE Class 4 Mathematics Time and Work MCQs on educational websites like studiestoday.com, online tutoring platforms, and in sample question papers provided on this website.
To prepare for Time and Work MCQs, refer to the concepts links provided by our teachers and download sample papers for free.
Yes, there are many online resources that we have provided on studiestoday.com available such as practice worksheets, question papers, and online tests for learning MCQs for Class 4 Mathematics Time and Work
Yes, you can find printable Time and Work worksheets for CBSE Class 4 Mathematics on studiestoday.com.
We have provided full database of free multiple choice questions with answers on studiestoday.com for CBSE Class 4 Mathematics Time and Work